Hi Folks,
I am trying to explore options of running MRP at Sloc level without activating MRP areas. Below is the data:
Material ABC, Current stock '0'
MRP type: PD
Lot Size : EX
For Sloc 0004, we have in MRP4 view:
SLoc MRP indicator = 2
Reorder qty = 3
Replenishment qty = 5
For Sloc 0005, we have in MRP4 view:
SLoc MRP indicator = 2
Reorder qty = 5
Replenishment qty = 7
When I run MD03 with parameters NETCH, 2,3,1,1,1, I get a Preq created for a total qty of 12. How do i get a separate requisition of qty 5 and 7? We are not a manufacturing company so MTO or MTS scenarios do not apply here.
Many thanks in advance,
Syd